Project Management

Information Technology Management· 4 CUs· E015
Performance assessmentDue Feb 25, 2027
Projects, roles and life cycles

Projects, programs, portfolios and operations

12 min

Project: a temporary endeavor undertaken to create a unique product, service or result. Temporary means a defined start and end, not a short duration.

TermMeaningIT example
ProjectTemporary, unique resultMigrate email to a cloud platform
OperationsOngoing, repetitive workRunning the help desk
ProgramRelated projects managed together for combined benefitsAll projects of a company-wide ERP rollout
PortfolioProjects, programs and operations managed together to meet strategic objectivesThe IT department's full investment list
PMO typeControl over projects
SupportiveLow: templates, training, lessons learned
ControllingModerate: requires compliance with methods and reviews
DirectiveHigh: PMO staff manage the projects directly
Organization structureProject manager authority
FunctionalLittle or none; functional manager controls staff and budget
Weak matrixLow; PM acts as coordinator or expediter
Balanced matrixLow to moderate; shared with functional manager
Strong matrixModerate to high
ProjectizedHigh to almost total; team reports to the PM

In a matrix, team members report to two bosses. The stronger the matrix, the more authority the PM holds.

Knowledge check

Which is a project?

A PMO that manages projects directly is:

In which structure does the project manager have the most authority?